Great Adventure Outpost

Latest Updates => Construction Updates => Topic started by: jglonek on December 15, 2008, 12:05:17 AM

Title: 10/05/05 El Toro Update
Post by: jglonek on December 15, 2008, 12:05:17 AM
10-5-2005

Welcome to our first update! Hopefully this will be the first of many El Toro and park construction updates as we follow all of the exciting changes that are coming for 2006.

(http://gadvupdates.com/10-5-2005Update/10-5-2005-1.jpg)
Crews begin pouring concrete behind what was once the Viper Station. Similar to how they started Kingda Ka, the workers are pouring a giant slab there for the Steel workers to work on when the weather get's soggy in the winter

(http://gadvupdates.com/10-5-2005Update/10-5-2005-2.jpg)
EVERYTHING has been cleared from this area to prepare for Plaza del Carnaval.

(http://gadvupdates.com/10-5-2005Update/10-5-2005-3.jpg)
A little peak under the soon-to-be El Toro station

(http://gadvupdates.com/10-5-2005Update/10-5-2005-4.jpg)
Will we EVER walk here again?

(http://gadvupdates.com/10-5-2005Update/10-5-2005-5.jpg)
They have excavated all the way over to Rolling Thunders first turn.

(http://gadvupdates.com/10-5-2005Update/10-5-2005-6.jpg)
Lumber for El Toro's structure waits to be erected

(http://gadvupdates.com/10-5-2005Update/10-5-2005-7.jpg)
Beautiful Intamin prefab track waiting to be installed

Thats it for now!